Splash Zone

  • Shell Norway

    Installation/location

    Draugen GBS, Norway

    Project

    Draugen-
    Concrete Inspection & Repair

    Description

    Repair of concrete surface (Grade B60) with hydraulic HP water cutting (2000 bar/32 l per minute),

    Dry spraying of mortar, Removal of epoxy,

    All work performed using Rope Access and suspended work platforms.

    Duration/manhours

    Annual campaigns 2008 – 2013. Approx. 8000 hrs. annually offshore.

  • Statoil

    Installation/location

    Flotell Superior / Vestbase, Kristiansund, Norway

    Project

    Flotell Superior Emergency repair of hull damages (time-critical)

    Description

    Project-management & Planning, Splash zone Inspection, Rigging, Rope Access and Mechanical / Welding, Hull (welding) repair with Cofferdam solutions, Prefab sheet metal and stiffeners for replacement, Removal of bolsters

    Duration/manhours

    December 2012. 5000 hrs. onshore (yard)

  • Statoil

    Installation/location

    Norne FPSO, Norway

    Project

    Norne Thruster Change

    Description

    Project-management & Planning, Diving (subcontractor), Rope Access, Rigging, Mechanical work.

    Duration/manhours

    2011. 2000hrs offshore.

  • Acergy

    Installation/location

    Harald Platform, Denmark

    Project

    Trym Riser Installation

    Description

    Verification of lifting plan, Removal and Replacement of 50tonns bumper,

    32 x M90 bolts in splash zone (HyTorc), Mounting and removal of lifting equipment

    Duration/manhours

    April – May 2010. 2000hrs offshore.

  • Statoil

    Installation/location

    Veslefrikk B platform, Norway

    Project

    Hull repair / Cofferdam solutions

    Description

    Project-management & Planning,

    Rope Access, Rigging, Mechanical work,

    Hull repair with Cofferdam solutions

    Duration/manhours

    2008. 2000hrs. offshore.

  • ExxonMobil

    Installation/location

    Balder FPSO, Norway

    Project

    Balder Thurster change

    Description

    Project-management & Planning,

    Diving (subcontractor),

    Rope Access, Rigging, Mechanical work

    Duration/manhours

    2008. 2000hrs offshore.

  • ConocoPhillips / Fabricom

    Installation/location

    Ekofisk platform, Norway

    Project

    Ekofisk 2/4B FTP By-pass

    Description

    Installation Planning

    Rigging, rope and mechanical

    Demolition of spider deck elements

    Installation of 4-ton clamp

    Assist divers with Installation of subsea clamps

    Lifting of the riser

    Extensive topside modifications

    Duration/manhours

    2006 – 2008. 20.000 hrs offshore.

  • ExxonMobil

    Installation/location

    Jotun B, Norway

    Project

    Riser Inspection, Jotun B

    Description

    Installation Planning,

    Rigging, rope access and mechanical,

    Splash zone Inspection,

    All work performed using Rope Access solutions.

    Duration/manhours

    2011. 1000hrs offshore.

  • AF Decom

    Installation/location

    Indiefield /Juliett, UK

    Project

    Indiefield /Juliett Decommissioning

    Description

    Planning the demolition operations (incl. splash zone), Access Planning,

    Rope Access , Rig + LOLER. rep , Mechanical (cutting, welding)

    Duration/manhours

    Annual campaigns 2009 – 2013. Approx 10.000 hrs annually offshore.